Types of Connection Updates Available
| Update Type | When You Need It |
|---|---|
| Name change | Property purchased, landlord change, account holder deceased, spelling error on bill |
| Load extension | Adding new ACs, industrial equipment, commercial expansion requiring more kW |
| Meter relocation | Meter needs to move to a different position on the property |
| Category change | Domestic to commercial, or correcting a wrong category already on the account |
| Phase change | Single-phase to three-phase when load requirements increase |
| Tariff correction | Billed under wrong tariff category (commercial vs residential, etc.) |
General Procedure — Applies to All Connection Updates
The process is broadly the same regardless of which specific change you need:
Step 1 — Visit your subdivision office. Bring your CNIC (original and photocopy), your most recent electricity bill, and any supporting documents specific to your change type (details below).
Step 2 — Submit a written application. A brief letter or the standard application form (available at the counter) stating your reference number, your name, and exactly what change you're requesting.
Step 3 — Document verification. The subdivision officer checks your identity and ownership documentation against the account records.
Step 4 — Technical inspection if required. Load extensions, meter relocations, and phase changes require a field visit by a technical team to confirm feasibility.
Step 5 — Payment of applicable charges. Some changes carry processing fees or infrastructure costs — load extensions and phase upgrades particularly. Get a written quote before proceeding.
Step 6 — Implementation and confirmation. Once approved, changes are made in MEPCO's system and reflected on the following bill. Get a written confirmation from the office with a reference number.
Name Change — Documents Required
A name change is one of the most requested updates — typically after a property sale, after a tenant vacates, or to correct a historical error.
Documents:
- CNIC of the new registered consumer (original + copy)
- Property ownership document showing the new owner's name (sale deed, registry, mutation, or allotment letter)
- If the original account holder is deceased: death certificate + legal heirship certificate
- If you're a tenant with owner authorization: rent agreement + owner's written authorization + owner's CNIC copy
- Most recent electricity bill
Processing time: 7 to 15 working days. Change reflects on the next bill after approval.
Load Extension — Documents Required
If you're adding significant new electrical load — another AC, industrial machinery, a new floor to the building — you need a formal load extension before the equipment runs, not after.
Documents:
- CNIC
- Existing electricity bill
- Written application specifying the additional load required (in kW)
- In some cases, a licensed electrician's letter confirming the installation plan
What happens: A technical team surveys the site to confirm existing infrastructure can handle the additional load. If it can't, you may be asked to bear the cost of infrastructure upgrades (transformer upsizing, additional poles, etc.) before the extension is approved. Operating above your sanctioned load without approval risks detection bill proceedings.
Processing time: 2 to 4 weeks including site survey.
Meter Relocation — Documents Required
If your meter needs to physically move — because of construction, safety concerns, or the meter's current position being inaccessible — a relocation request is the correct process.
Documents:
- CNIC
- Existing bill
- Written application explaining the reason for relocation and the proposed new location
What to expect: A technical team visits to assess feasibility and quote any wiring adjustment costs. The meter is moved only after payment of applicable charges. You are responsible for ensuring the new location meets MEPCO's access requirements — the meter reader must be able to reach it without entering locked private areas.
Category Change — Documents Required
If your connection is currently billed under the wrong category (commercial rates on what should be a domestic connection, or agricultural tariff where commercial should apply), a category correction can be requested.
Documents:
- CNIC
- Existing bill
- Evidence supporting the correct category (property ownership type, business registration if commercial, nature of use)
Note: A category change can work both ways — if you're currently benefiting from a domestic rate on what is actually commercial use, applying for a category change may increase your bill. Get clarity on the likely outcome before proceeding.
Common Reasons Updates Are Delayed
Incomplete documentation at first submission — the most common cause. Bring originals and copies of everything listed for your specific change type before the visit.
Missing owner authorization for tenants — if you're a tenant and the bill is in the landlord's name, or vice versa, anything beyond a basic inquiry requires explicit authorization from the registered account holder.
Technical feasibility issues for load extensions — if the local infrastructure cannot support additional load, the extension is delayed until either the infrastructure is upgraded or the request is modified.
Pending arrears on the account — most update requests require the account to be in good standing (no overdue bills). Clear any arrears first.
Frequently Asked Questions
How do I change the name on my electricity connection?
Visit your subdivision office with your CNIC, the latest bill, and property ownership documentation showing the new name. Processing takes 7 to 15 working days and the change reflects on the following billing cycle.
Can I increase my sanctioned electricity load without visiting the office?
No — load extensions require a formal application, site inspection, and formal approval before any additional load can be added. Operating above your sanctioned load without approval risks a detection notice.
How long does a meter relocation take?
Typically 2 to 4 weeks from application to completion, depending on site survey scheduling and whether any infrastructure work is required.
Can I change from a commercial to domestic tariff category?
Yes, if your connection and property genuinely qualify for domestic tariff. A site survey will be conducted, and the change is only approved if the usage and property type confirm the domestic classification is correct.
What happens if I don't formally apply for a load extension and just add more equipment?
Operating beyond your sanctioned load is classified as unauthorized load use — one of the triggers for a detection bill under the Electricity Act. The formal extension process exists to prevent this outcome.
Last updated: August 2026